EBH & Associates, P.A., was selected by the City of Holton, Kansas, to design their wastewater collection system improvements. Holton had a 38 year old system that had exhausted its life cycle. The distribution system includes over 30 miles of water lines ranging from 2-12 inch consisting of both cast iron and PVC. The distribution system also includes over 100 fire hydrants. The city water plant has a production capacity of 1.0 MGD.

Holton Makes Water Improvements



ProjectsProject Information

Services Provided
  • Wastewater Collection and Treatment
Project Details

There were multiple changes made during this project as not all point repairs had been made on the sewer mains that were set to be lined. EBH worked closely with the City of Holton and the contractor to make revisions to the initial plan when issues were encountered during the camera videoing process, prior to the lining. Cooperation between all parties was great and allowed for a smooth flowing project.

The project included:

  • Rehabilitation of sanitary sewer collection system including cleaning, videotaping and logging defects, prepping the line to receive cured in place pipe (CIPP)
  • Sewage pump around as required, approximately 8,082 L.F. of 8" CIPP, traffic control, and appurtenances
  • Additive Areas: Rehabilitation of sanitary sewer collection system including cleaning, videotaping and logging defects, prepping the line to receive cured in place pipe (CIPP)
  • Sewage pump around as required, approximately 1,466 L.F. of 8" CIPP, approximately 354 L.F. of 12" CIPP, traffic control, and appurtenances
Project Team
  • image description
    Andrew Brunner, PE