ProjectsVictoria Dollar Store Utilities 2023
Status:
Completed
Owner:
City of Victoria, Kansas
Location
Victoria, Kansas
The City of Victoria worked with EBH Engineering on the design of the water and utilities for the new Dollar General coming to town. The design included approximately 710 linear feet of 6” PVC water line and 400 linear feet 8” sewer line. This also included gate valves, service connections, fire hydrants, tracer wire test station, manholes, and appurtenances.
ProjectsProject Information
Services Provided- Subdivision and Site Planning
- Surveying
- Waterline Improvements
Components of this project included:
- Extend water distribution line, including service connection and fire hydrants
- Extend sanitary gravity sewer to serve proposed site
Project Team
-
Michael Younger, PE