ProjectsLyons ATP Utility Improvements 2021
Status:
Completed
Owner:
City of Lyons, Kansas
Location
Lyons, Kansas
The City of Lyons hired EBH Engineering to complete the engineering design on the ATP Facility. The project included installing looped water distribution line from Main St. to North end of Miles St. to provide fire protection and water service. The sanitary gravity sewer design has had to be extended in Miles St. corridor to serve proposed facility. EBH also defined the easement boundaries to facilitate water, sewer, and gas system improvements to facility. Design also included improvements on the Courthouse Sanitary Sewer System.
ProjectsProject Information
Services Provided- Wastewater Collection and Treatment
Major work included:
- Installing approximately 697 l.f. of 8” SDR 26 PVC sewer main
- Installing manholes and appurtenances
-
Michael Younger, PE
-
Richard Ammel, PE