Projectsimage descriptionPeabody KDOT Cost Share Street Improvements 2020

Status: Completed
Owner: City of Peabody, Kansas
Location
Peabody, Kansas
Addendum ADDENDUMS NO. 1 & 2

image description

The City of Peabody will receive sealed bids for the 2020 Peabody KDOT Cost Share Street Improvements at the online plan room of EBH Engineering (https://ebhengineering.com/plan-room/) until 3:00 P.M. Monday, May 10, 2021.. Bids received after this time will not be accepted.  Bids will be opened and read aloud immediately after the specified closing time.

STREET IMPROVEMENTS: (Major Items of Work)

Sycamore Street from 7th St to 9th St, 4th Street/Elm Street Intersection and 4th Street from Pine St to Elm St

230 square yards of 8” Concrete Valley Gutter; 4000 square yards of 6” Concrete Pavement; 2,450 square yards of 6” Concrete Entrance Pavement; 2,900 linear feet of Curb & Gutter; 1,925 cubic yards of Common Excavation; 8,123 square yards of 4” Crushed Rock Base over Geogrid; 285 square yards of 4” Sidewalk; Seeding and Traffic Control.

Bidding Documents may be examined at City of Peabody and at the Engineer’s office.  They are available for download at the online plan room of EBH Engineering (https://ebhengineering.com/plan-room/)

The project will be reviewed for compliance with the Bid Documents, and the OWNER reserves the right to award the contract to the lowest responsible, responsive bidder.

OWNER reserves the right to waive irregularities and to reject any and/or all bids.